Athens International Airport S.A.(...) is inviting
companies or consortia/ joint ventures to tender for the Works in title at
Athens International Airport "Eleftherios Venizelos".
The overall scope includes all required works for the full, complete, faultless
and ready-to-use implementation of the STB Enhancement Project - Phase
III.
Phase III of the project is mainly characterized by the eastern expansion
of the building by 1400m², split into two (2) levels (arrivals & departures),
with certain operational re-arrangements throughout the terminal that may
be briefly summarized as follows:
Following the successful implementation of phases 1 & 2 of the Satellite
Terminal Building (STB) Enhancement project, AIA is further developing
the operational, commercial and aesthetic ambience of the STB. In view of
phase 3 of the project, AIA is launching the present scope, which is mainly
characterized by the following:
1. The construction of two (2) additional STB Intra-Schengen Walkout Gates, to be designed at the western side of level 1;
2. The construction of two (2) STB Extra-Schengen Walk-out Gates,
to be designed at the eastern side of level 1, outside the building
envelope;
3. The widening of the passport control queueing area at both
departures’ & arrivals level, to accommodate additional passport
booths, for serving the increased traffic demand.
More details will be included in the Tender Documents which will be
dispatched to the interested applicants.
Estimated award: February 2020
Construction Completion: June 2020
Term completion (including Liability Period): June 2022
The estimated total contract value amounts to € 7,7 million